Flat villa roof flooded with about 5 cm of water over the waterproofing membrane, with the rain drain plugged for a leak test

Flood-test your roof for 24 hours

Before the screed or tiles go on, plug the roof drains and cover the membrane with about 5 cm of water. Leave it at least 24 hours (48 is better), then check the ceilings and walls below for damp. Dry? Drain slowly and carry on. Damp? Fix it before anything covers it.