How much does it cost to build a villa in Riyadh in 2026?

Structure, finishing and turnkey prices per m² in Riyadh, a worked example for a 400 m² villa, and the extra costs most owners forget.

By SouqHouseUpdated Nov 3, 20263 min readRiyadh
Two-floor villa under construction in Riyadh, with concrete frame and blockwork finished

Building a 400 m² villa in Riyadh with standard finishing costs about SAR 715,000 to 945,000 in 2026, land not included. Below: the price per m² at each stage, how we got to that total, and what makes your own number go up or down.

Price per m² in Riyadh in 2026

Prices are per square metre of built area (all floors added together).

StageSAR per m²
Structure with materials (concrete, steel, blocks)500 – 750
Turnkey, economy finishing1,100 – 1,500
Turnkey, standard finishing1,500 – 2,000
Turnkey, premium finishing2,000 – 2,800 and more
Basementup to 1,500

Example: a 400 m² villa with standard finishing

  • Construction: 400 m² × SAR 1,500–2,000 = SAR 600,000–800,000
  • Contingency (15%, recommended by most engineers): SAR 90,000–120,000
  • Soil test, electricity connection, hidden-defects insurance: about SAR 25,000
  • Total: about SAR 715,000–945,000, excluding land, design and permit fees

Try your own numbers with the renovation cost estimator.

Don't start from the land price

Many owners budget the land and the construction, then run out of money at the end. Add these lines from day one:

  • Architectural and structural design, and the building permit
  • Soil report (about SAR 3,000–5,000)
  • Electricity connection and meter (up to SAR 15,000 depending on the load)
  • Hidden-defects insurance (Malath), about 1.5% of the structure cost
  • Independent site supervision (1–3% of the project)
  • Boundary wall, gate, landscaping and outdoor lighting
  • Kitchen, wardrobes, AC units and water heaters if they are not in the contract

What makes the price go up or down

  • Finishing level. It is the biggest swing: premium finishing can cost almost twice the standard level.
  • Basement. Excavation and waterproofing make it the most expensive square metres of the house.
  • Facade. Natural stone and large glass areas cost much more than paint or GRC.
  • AC system. Central or ducted systems cost more than split units but last longer.
  • Changes during the works. Every change after the contract adds cost and delay. Fix the plans before you sign.

How to get a reliable price

  1. Finish the drawings and a list of materials (brands, sizes, finish level) first.
  2. Send the same file to at least 3 contractors and compare line by line, not just the total.
  3. Check each contractor's past villas and reviews.
  4. Pay by finished stage, never a large advance.

Check current material prices in the materials price index.

Prices are indicative ranges, last updated Nov 3, 2026. The final price depends on the site, the materials and the pro.