Bathroom renovation cost in Riyadh and Dubai: price per item

SAR 9,000–19,000 in Riyadh, AED 25,000–45,000 in Dubai for a standard bathroom: the price of each item, from demolition and waterproofing to tiles and sanitary ware.

By SouqHouseUpdated Nov 17, 20265 min read
Bathroom renovation cost in Riyadh and Dubai

A full bathroom renovation costs about SAR 9,000–19,000 in Riyadh and AED 25,000–45,000 in Dubai for a standard 4–7 m² bathroom, stripped back and rebuilt. Sanitary ware, the vanity and the tile choice decide most of the gap between the low and high end: the labour lines move much less.

Bathroom renovation prices at a glance

ItemRiyadh (SAR)Dubai (AED)
Demolition and debris removal1,000–2,0001,500–3,500
Plumbing renewal, no relocation2,500–5,0002,000–4,000
Electrical: lights, fan, heater circuit500–1,2001,500–3,500
Screed to fallsnot priced separately1,200–2,500
Waterproofing with flood test1,200–2,5002,000–5,000
Tiles, per m² of floor and wall45–130 supplied and fixed50–150 supply + 60–130 fixing
Sanitary ware and mixers2,000–8,0004,000–15,000
Glass shower screen1,800–4,5001,500–6,000
Vanity, mirror, joineryquoted with the basin set2,500–12,000
Ceiling, paint, ventilation90–140 per m² of ceiling1,000–3,000
Full renovation, 4–7 m²9,000–19,00025,000–45,000

1. Demolition: strip back to the blockwork

Removing old tiles, fixtures and screed, and taking the debris away, costs SAR 1,000–2,000 in Riyadh and AED 1,500–3,500 in Dubai. Laying new tiles over old ones saves this line, but only if the plumbing and the waterproofing underneath are sound. If you have a leak, strip back.

2. Plumbing and electrical

Renewing the supply and drain pipes in the same positions costs SAR 2,500–5,000 or AED 2,000–4,000. Moving the toilet or the shower drain costs more, because the floor and the falls change. Electrical work covers lights, the extract fan and the water heater circuit. Size the heater first with the water heater guide.

3. Waterproofing: the line not to cut

A membrane on the floor and up the shower walls, then a 24–48 hour flood test, costs SAR 1,200–2,500 or AED 2,000–5,000. It is a small part of the total, and a failed membrane means stripping the new tiles to repair it. Ask to see the flood test before the tiler starts.

4. Tiles: the biggest swing

A standard bathroom has about 25–30 m² of tiled floor and wall. In Riyadh, guides give SAR 45–130 per m² with tiles supplied and fixed. In Dubai, contractors price the tiles (AED 50–150 per m² for porcelain) and the fixing (about AED 60–130 per m²) separately. Large-format slabs and marble cost several times more. Work out your quantity with the tile calculator and add 10% for cuts.

5. Sanitary ware, glass and vanity

  • Toilet, basin and mixers: SAR 2,000–8,000 or AED 4,000–15,000. A wall-hung toilet with a concealed cistern sits at the top of the range.
  • Glass shower screen: SAR 1,800–4,500 or AED 1,500–6,000, depending on size and frameless glass.
  • Vanity and mirror: in Dubai, AED 2,500–12,000; in Riyadh, ask for it as a separate line.

Before you choose, check the sizes in our bathroom dimensions guide: a 90 × 90 cm shower and 76 cm clear in front of the toilet change what fits.

6. Ceiling and finishing

A moisture-resistant gypsum ceiling with lights costs SAR 90–140 per m² in Riyadh. In Dubai, ceiling, paint and ventilation together come to AED 1,000–3,000. See our gypsum ceiling cost guide for the details.

7. Time and permissions

Guides give 10–18 working days in Riyadh and 18–25 working days in Dubai, where the flood test and building rules add time. In a Dubai apartment or community, the building or developer usually asks for a renovation NOC, about AED 500–2,000.

Example: a 2.5 × 2 m bathroom, fully renovated

Floor 2.5 × 2 = 5 m². Walls tiled to 2.4 m: 2 × (2.5 + 2) × 2.4 = 21.6 m², minus the door (0.9 × 2.1 = 1.9 m²) = 19.7 m². Tiled area: 5 + 19.7 = about 25 m².

Riyadh (SAR)

  • Demolition 1,000–2,000; plumbing 2,500–5,000; electrical 500–1,200; waterproofing 1,200–2,500
  • Tiles: 25 × 45 = 1,125 to 25 × 130 = 3,250
  • Sanitary ware 2,000–8,000; glass screen 1,800–4,500
  • Ceiling: 5 × 90 = 450 to 5 × 140 = 700
  • Total: SAR 10,575 to SAR 27,150; with 15% VAT: 10,575 × 1.15 = SAR 12,161 to 27,150 × 1.15 = SAR 31,223

Dubai (AED)

  • Strip-out 1,500–3,500; plumbing 2,000–4,000; electrical 1,500–3,500; screed 1,200–2,500; waterproofing 2,000–5,000
  • Tiles: 25 × 50 = 1,250 to 25 × 150 = 3,750, plus fixing 1,600–3,500
  • Sanitary ware 4,000–15,000; glass screen 1,500–6,000; vanity 2,500–12,000; ceiling and paint 1,000–3,000
  • Total: AED 20,050 to AED 61,750; with 5% VAT: 20,050 × 1.05 = AED 21,053 to 61,750 × 1.05 = AED 64,838

In both cities, sanitary ware, the vanity and the tiles make up most of the gap between the two totals. Choose them first, then ask for prices.

How to get a reliable price

  1. Measure the bathroom and count the tiled area: floor plus walls, minus the door.
  2. Choose the fittings first: toilet, basin, mixers, shower screen, vanity. The price depends on them more than on the labour.
  3. Ask for a line-by-line quote with the same rows as the table above, and with VAT shown.
  4. Write the flood test into the quote, with the date it will happen, before any tile is laid.
  5. Get 3 quotes from verified bathroom and tiling pros: post your job for free and compare them line by line.

Prices are indicative ranges, last updated Nov 17, 2026. The final price depends on the site, the materials and the pro.