SAR 60,000–85,000 in Riyadh, AED 120,000–230,000 in Dubai for an 8 × 4 m concrete pool: what a villa pool costs in 2026, the chiller, approvals and running costs.
A standard 8 × 4 m concrete pool for a villa costs about SAR 60,000–85,000 in Riyadh and AED 120,000–230,000 in Dubai in 2026, before a chiller and other extras. An overflow pool costs about 1.5–2 times as much, or more in Dubai. Running it costs about SAR 500–1,000 or AED 1,000–1,800 a month.
Pool costs at a glance (8 × 4 m villa pool)
Item
Riyadh (SAR)
Dubai (AED)
Fibreglass pool
35,000–55,000
75,000–180,000
Concrete pool, skimmer
60,000–85,000
120,000–230,000
Concrete pool, overflow or infinity
95,000–145,000; infinity 160,000+
280,000–500,000+
Pool chiller or heat pump
12,000–25,000
15,000–40,000
Salt chlorinator
4,000–8,000
8,000–25,000
Rock in the excavation
+8,000–15,000
up to +50,000 for ground problems
Drawings and approvals
permit fee on Balady
8,000–25,000
Running costs, per month
500–1,000
1,000–1,800
1. Concrete or fibreglass
A fibreglass pool is a factory-made shell dropped into the hole. It is the cheapest option and goes in fast: in Riyadh, installation takes about two weeks. But the shapes and sizes come from a catalogue.
A concrete pool is built on site, so any size, shape or depth is possible, and it lasts longer. It is the usual choice for Gulf villas. The difference between a skimmer and an overflow pool is the edge:
Skimmer: the water sits a little below the edge and is drawn off through side openings. Simpler and cheaper.
Overflow: the water spills over the edge into a channel and a balance tank. It looks better and costs much more.
2. What the pool price usually covers
A full quote for a concrete pool should include the excavation, the reinforced concrete shell, waterproofing with a water test before tiling, the pipes, the pump and filter in a plant room, lights and standard tiles. The pumps, filters and plant room alone make up about 20–30% of a Riyadh pool budget.
Usually extra: the chiller, salt or UV treatment, glass mosaic, decking beyond the coping, landscaping, a safety fence, a pool cover and automation.
3. The chiller: not optional in the Gulf
From June to September, pool water gets too warm to be refreshing. A chiller or a combined heat-and-cool pump costs SAR 12,000–25,000 in Riyadh and AED 15,000–40,000 in Dubai. A combined heat-and-cool system in Dubai can reach AED 30,000–65,000. Plan the space and power for it from the start, even if you add it later.
4. Finishes and site conditions
Tiles: local pool tiles cost about SAR 40–70 per m²; Spanish glass mosaic SAR 120–300 per m². Mosaic can add 30–50% to the finishing budget. Estimate the quantity with the tile calculator.
Depth: a pool deeper than 1.5 m costs about 15–20% more.
Rock: in harder ground, such as north Riyadh, breaking rock adds SAR 8,000–15,000.
5. Approvals
Riyadh: include the pool in the villa's drawings and permit on Balady. For an existing villa, it goes through Balady's service for adding and amending building components. See our building permit guide.
Dubai: the pool's plans must be approved before work starts, by Dubai Municipality or the authority for your area, and many communities also ask for a developer NOC. Dubai's public safety law, in force since 1 June 2026, covers swimming pools, including those at homes. Municipality guidance asks for a barrier at least 1.2 m high with a self-closing gate.
6. Running costs
Plan SAR 500–1,000 a month in Riyadh for pump electricity, water lost to evaporation and chemicals. In Dubai, guides give AED 1,000–1,800 a month: chemicals AED 250–400, a service contract AED 400–800 and electricity for the pump and chiller AED 300–700.
Example: an 8 × 4 m concrete skimmer pool with a chiller
Water area: 8 × 4 = 32 m².
Riyadh (SAR)
Pool: 60,000–85,000
Chiller: 12,000–25,000
Salt chlorinator: 4,000–8,000
Total: 60,000 + 12,000 + 4,000 = SAR 76,000 to 85,000 + 25,000 + 8,000 = SAR 118,000; with 15% VAT if excluded: 76,000 × 1.15 = SAR 87,400 to 118,000 × 1.15 = SAR 135,700
Running: 12 × 500 = SAR 6,000 to 12 × 1,000 = SAR 12,000 a year