Building permit in Saudi Arabia: the steps before work starts
Deed, survey decision, soil test, an accredited design office and Balady: the steps to a villa building permit in Saudi Arabia, the setbacks and a worked example.
In Saudi Arabia, no villa work can start without a building permit issued on Balady, and you don't apply alone: a design engineering office accredited by the Ministry applies for you. Once the drawings are ready, Balady lists the service at 1–10 days, and the permit stays valid for 3 years. Most delays happen before that: deed, survey decision, soil test and drawings.
The building permit at a glance
Step
Who does it
Key number
Updated electronic deed
You (Ministry of Justice)
Must be current
Survey decision (القرار المساحي)
Engineering office, on Balady
Valid 3 years
Soil study report
Soil testing lab
Required for the permit
Drawings and application
Design office you delegate on Balady
Accredited by the Ministry
Supervising office and contractor
Chosen on Balady
Contractor must be classified
Review and issue
Municipality and technical examiner
1–10 days on Balady
Permit
Renewable from 90 days before expiry
Valid 3 years
Occupancy certificate
After the works
Permit at least 6 months old
1. Check the deed and the plot
Balady asks for an updated electronic deed from the Ministry of Justice. If your deed is old or on paper, update it first. Then note the width of every street around the plot: the setbacks below are calculated from it.
For villas, the residential building rules approved in 2024 set:
Setback
Rule
Front, street under 30 m
1/5 of the street width, at least 3 m
Side and rear streets
1/5 of the street width, at least 2 m
Front, street 30 m or wider
At least 6 m
Towards neighbours
At least 1.5 m
The same rules allow up to 75% ground-floor coverage. Your plot's approved plan can add its own conditions, so ask the design office to confirm them first.
2. Get the survey decision (القرار المساحي)
The survey decision fixes your plot's boundaries and dimensions for the permit. The engineering office can issue it on Balady, or you can pick an existing one. It is valid for 3 years; after that you apply for a new one. If you bought the plot next door, the two plots must be merged with a new survey decision before the permit.
3. Order the soil test
A soil study report is one of Balady's requirements. It tells the structural engineer what foundations the villa needs, so order it before the structural drawings, not after.
4. Hire a design office and delegate it on Balady
You log in to Balady with your national access, start a permit request and delegate an accredited design office. The office accepts, selects the survey decision and prepares the architectural and structural drawings to the Saudi Building Code. Villas for one or two families up to three floors follow the code's residential section.
5. Choose the supervising office and the contractor
Before the permit is issued, Balady requires a contract with a supervising engineering office and a construction contractor. The contractor must be classified on Balady. Choosing them now matters: the supervisor will check the work stage by stage, which is also how you should split the contractor's payments.
6. Review, fees and issue
A technical examiner, the municipality and any outside authority the project needs review the drawings. The design office then reviews the municipal fees, issues the invoice, and the permit is issued once the fees are paid. Some mandatory items are completed by the contractor directly on Balady, so read the full, current requirement list on the Balady building permit page before you plan your dates. The same service also issues a fencing permit if you only want to build the boundary wall first.
7. During and after the works
Build what the permit shows. Extra coverage, an extra floor or ignored setbacks must be removed at the owner's cost; where removal would harm the structure, the penalty is half the cost of the part that breaks the rules.
Changes go through Balady's service for adding and amending building components.
Renewal: if the work isn't finished in 3 years, renew from 90 days before expiry.
Occupancy certificate: issued for a permit at least 6 months old. It is needed to activate the permanent electricity supply, and Balady then issues the building compliance certificate on its own.
Example: setbacks on a 20 × 30 m plot
A villa plot with 20 m of frontage on a 20 m street, neighbours on the other three sides:
Front setback: 20 ÷ 5 = 4 m (more than the 3 m minimum)
Side and rear setbacks to neighbours: 1.5 m each
Buildable width: 20 − 1.5 − 1.5 = 17 m
Buildable depth: 30 − 4 − 1.5 = 24.5 m
Footprint: 17 × 24.5 = 416.5 m², under the 75% limit of 600 × 0.75 = 450 m²
On this plot the setbacks, not the coverage limit, decide the largest ground floor. The 400 m² villa in our villa cost guide needs only 400 ÷ 2 = 200 m² per floor, which leaves room for a garden and parking.
Before you call an engineering office
Update the deed and note the width of every street around the plot.
Check the survey decision: does one exist, and is it under 3 years old?
Order the soil test so the structural design starts on real data.
Compare accredited offices in the SouqHouse directory: design, supervision, and how many villas they have taken through Balady.