Contractor payments: how to split the payments for your villa

A small advance, payments tied to finished and checked stages, 5–10% held until the defects period ends: how to split your contractor's payments, with a full example.

By SouqHouseUpdated Nov 17, 20266 min read
contractor payments villa

Never pay a contractor more than the work on site is worth. Keep the advance between 0 and 10%, tie every other payment to a finished stage that your engineer has checked, and hold back 5–10% until the defects period ends. On an SAR 800,000 villa, that means about SAR 720,000 paid before you get the keys, SAR 40,000 at handover and SAR 40,000 when the defects period ends.

Contractor payments at a glance

ItemTypical share of the contractWhen you pay it
Advance0–10%After signing, when the team and equipment are on site
Structure (العظم)about 30–40%In 4–5 payments, each after a slab or a floor is finished and checked
Blockwork, MEP, plasterabout 20–25%After each trade is finished and checked
Finishingabout 25–30%Tiling, ceilings, paint, doors, kitchen, sanitary ware
Handover5%After the snagging list is closed
Retention5–10%At the end of the defects period

1. Keep the advance small

An advance pays for mobilising the team, not for work that hasn't been done yet. Saudi villa contracts vary: one published model contract for the structure has no advance at all and splits the price into 13 stages of 7–8%, while a turnkey model asks for 10% at signing. Treat 10% as a ceiling, not a starting point. Pay it only once the contract is signed and the contractor is actually on site.

2. Tie every payment to a finished, checked stage

Each payment should match a stage you can see and check: foundations poured, a slab cast, blockwork finished. Before you pay, your supervising engineer (المهندس المشرف) in Saudi Arabia, or the consultant in Dubai, checks the work and signs off the payment request. In Dubai Municipality's guidance contract for consultants, the consultant checks each payment request within 7 days.

Here is an example split for a turnkey villa (ground floor, first floor and roof annex):

#Stage finished and checkedShare
1Contract signed, team on site (advance)5%
2Excavation, footings, grade beams (الميدة) and foundation waterproofing8%
3Ground-floor columns and roof slab10%
4First-floor columns and roof slab10%
5Roof annex (الملحق) slab and parapets (الدروة)5%
6Blockwork on all floors8%
7Plumbing, electrical and AC rough-in, before plaster8%
8Plaster, roof waterproofing and insulation9%
9Tiling and gypsum ceilings12%
10Paint, doors, kitchen, sanitary ware and fittings15%
11Handover, after the snagging list is closed5%
12Retention, at the end of the defects period5%

Adapt the shares to your own quote. The test is simple: at each payment, the total you have paid should stay at or below the value of the work done. Check each stage with the site inspection checklist.

3. Hold back a retention

The retention is the part of the price you keep until the defects period is over. It gives the contractor a reason to come back and fix cracks, leaks or loose tiles. 5–10% is the usual range, and 10% is common in the UAE. Write in the contract how long the defects period lasts (Saudi contracts commonly set one to five years) and that the retention is released only when every defect on the list has been fixed.

4. Structure-only and labour-only contracts

Many Riyadh villas are built in two contracts: the structure (العظم) first, then finishing. Structure contracts are often priced per m², so the last payment comes after the final measurement (التمتير) of the built areas on site. If you buy the materials yourself and pay only for labour (مصنعية), pay the labour per finished stage in the same way, and keep your own record of every material delivery.

5. What the written contract must say

  • The scope: approved drawings, specifications and the brands of the main materials.
  • The payment table, stage by stage, and who signs off each stage.
  • The duration and the delay penalty. One Saudi model contract sets SAR 1,000 per day, capped at 10% of the contract value.
  • How variations are agreed, priced and signed.
  • The retention, the defects period and when it ends.
  • Whether the price includes VAT: 15% in Saudi Arabia, 5% in the UAE.

In Saudi Arabia, the Contractors Authority offers electronic model contracts on the Muqawil platform, with payment tables, delay penalties and payments linked to progress. In Dubai, the Municipality publishes guidance contracts for private villas. Both are a good base for your own contract.

6. Variations: in writing, before the work

Changing a window size or adding a room is normal. Paying for it later without a written price is how disputes start. Ask for a written variation with the price and the effect on the duration, sign it, and add it to the payment table before the work starts.

7. If the work stops or goes wrong

Don't pay ahead to keep a contractor on site. Under Saudi law, if the contractor breaches the contract, you can give written notice to put it right within a reasonable time, then end the contract or hand the work to another contractor at his cost. After handover, the contractor and the supervising engineer remain jointly responsible for 10 years for a collapse or a hidden defect that threatens the structure, in Saudi Arabia and in the UAE.

Example: an SAR 800,000 villa

A 400 m² villa with standard finishing in Riyadh, at the top of the 2026 villa cost range, with the split above:

  • Advance: 800,000 × 5% = SAR 40,000
  • Structure (stages 2–5): 800,000 × (8 + 10 + 10 + 5)% = 800,000 × 33% = SAR 264,000
  • Blockwork, rough-in, plaster (stages 6–8): 800,000 × 25% = SAR 200,000
  • Finishing (stages 9–10): 800,000 × 27% = SAR 216,000
  • Paid before the keys: 40,000 + 264,000 + 200,000 + 216,000 = SAR 720,000 (90%)
  • Handover: 800,000 × 5% = SAR 40,000
  • Retention after the defects period: 800,000 × 5% = SAR 40,000

If the SAR 800,000 excludes VAT, add 15%: 800,000 × 1.15 = SAR 920,000 in total.

Before you sign with a contractor

  1. Get the drawings and specifications approved first, so every quote prices the same villa.
  2. Ask for a price with a stage table, not a lump sum with an advance. Use the renovation estimator for a first budget.
  3. Name the engineer or consultant who will sign off each stage.
  4. Check the critical stages yourself, for example roof waterproofing before the tiles cover it.
  5. Get 3 quotes from verified contractors: post your job for free and compare the payment tables side by side.